The Albertville School System is involved with several constructions projects at this time. The highlight of these projects is the construction of a new Albertville High School. The schedule of the various projects is found below:
 
PROJECT                                   STARTED                         COMPLETED DATE
                                                                                              (Expected Completion Date)
ALBERTVILLE HIGH SCHOOL:
McCord Field                                                                                   09.10.08
 
AGGIE Cafeteria                                                                               09.28.08
 
Maintenance Building                                                                         11.27.08
 
Performing Arts Building                   06.20.08                                    10.03.09
 
Class Room Building                         11.01.08                                   08.10.10
 
New Gymnasium                               10.01.09                                   10.01.10
 
Track                                                01.01.10                                   01.01.11
 
ALBERTVILLE ELEMENTARY Project:
                                                         05.03.08                                    08.12.08